sched/fair: Make sure to try to detach at least one movable task

During load balance, we try at most env->loop_max time to move a task.
But it can happen that the loop_max LRU tasks (ie tail of
the cfs_tasks list) can't be moved to dst_cpu because of affinity.
In this case, loop in the list until we found at least one.

The maximum of detached tasks remained the same as before.

Signed-off-by: Vincent Guittot <vincent.guittot@linaro.org>
Signed-off-by: Peter Zijlstra (Intel) <peterz@infradead.org>
Link: https://lkml.kernel.org/r/20220825122726.20819-2-vincent.guittot@linaro.org
This commit is contained in:
Vincent Guittot 2022-08-25 14:27:23 +02:00 • committed by Peter Zijlstra
commit b0defa7ae0